Buildfast Building Timeframe Guarantee
Subject to the terms and conditions below, the Builder hereby guarantees to achieve “Practical Completion” of the “work” within 24 weeks from completion of concrete slab down stage or will pay the Owner/s $300 per week for every week that completion is delayed.
Conditions
The site must be within the Perth Metropolitan area and all services including power, water and gas must be available
This guarantee will not include the installation of fencing and landscaping
Unit developments, battle axe blocks, house behind house sites and narrow lot sites are excluded from this guarantee
No owner supplied materials will be permitted
No variations to the “works” will be accepted during the construction process
For the purpose of this annexure, clause 11(b) of the Building Contract will still apply
Public holidays occurring during the construction process will be added to the 24 week time frame
 
Fixed Price Siteworks Guarantee
Fixed cost siteworks are based on historical evidence for the suburb the home is being built in as collated in the Impressions siteworks manual. These costs only apply for green titled sandy, benched, flat level A class sites with a D10 footing detail, water, power and sewer provided in the Perth Metro area. Cost includes earthworks, compaction, stormwater removal, sewer, underground power, water and gas run ins. Any unforeseen costs, such as but not limited to removal of existing structures, buried material, tree removal and retaining are not included. Fixed Sitecosts do not include Bushfire Attack Level or Noise attenuation costings should they be required.